June 2019

Asphalt started
Rock wall completion
Training ground completion
Exterior concrete completion
Permanent power
Bay doors installed

May 2019

Ceiling Grid Started
Cabinets Started
Metal Siding Completed

April 2019

MEP Rough-in Completed
Flat Work (Outside Concrete)
Started
Interior Paint Started

March 2019

Insulation Started
Metal Siding Started
Roofing Started
Gypsum Wall Board (GWB) Started

Read more…

February 2019

Windows Completed
Siding Started

January 2019

Water Main Completed
Framing completed
Mechanical, Electrical, Plumbing (MEP) Rough-in Started

December 2018

Framing is underway

Read more…

September 2018

Inspections Begin at New Bayview Station

Read more…

August 2018

Bayview Fire Station About to Break Ground

Read more…

July 2018

Local firm selected to build new fire station.

Read more…

April 2018

Building permits issued.

January 2018

The building design is approved and waiting for the permits to be issued.

Cost estimates are out.

June 2017 to January 2018

Work continues with the architects and Island County for additional modifications of the building plans.

May 2017

Building plans submitted to Island County for the building permits for review.

April 2017

South Whidbey Fire/EMS is issuing Limited Tax General Obligation Bonds to pay the costs of constructing and equipping a new replacement fire station on its Bayview property.

Read more…